2005 Andhra University MCA OPERATIONS RESEARCH Question paper for exam preparation. Question paper for 2005 Andhra University MCA OPERATIONS RESEARCH Question paper, 2005 Andhra University MCA OPERATIONS RESEARCH Question paper. SiteMap
K2Questions Logo


2005 Andhra University MCA OPERATIONS RESEARCH Question paper

University Question Papers
2005 Andhra University MCA OPERATIONS RESEARCH Question paper

MCA 2.2.3

OPERATIONS RESEARCH

First Question is Compulsory

Answer any four from the remaining

Answer all parts of any Question at one place.

Time: 3 Hrs.
Max. Marks: 100

1. Write short notes on the following:
a) Graphical Method for solving a Linear Programming Problem.
b) Explain the Duality in linear programming.
c) Zero sum Game.
d) Economic order Quantity (EOQ).
e) Min-Max Method.

2. a) Explain the characteristics of LP model.

b) Solve the following LP problem by using Simplex method:
Minimize : z = 2x1 + 4x2 + x3
Subject to 4x1 + 8x2 + 2x3 = 40
-3x1+2x2 = 6
x+2x+x=24
x1, x2, x3 = 0

3. a) Explain the reasons for analysing a primal linear programming problem in terms of dual form.

b) Given the following linear programming problem:
Minimize z = 4x1 + 3x2
Subject to :
2x1 + x2 = 10
-3x1 + 2x2 = 6
x1 + x2 = 6
x1 , x2 = 0
Solve using the dual simplex method.

4. a) Explain the Transportation and Transhipment problems.
b) Given the following Transportation problem:

To A B C D Supply
From
1 5 12 7 10 50
2 4 6 7 6 50
3 2 8 5 3 60
Demand 40 20 30 70

Find the initial solution by VAM method and optimum solution by MODI method.

5. a) Explain the Travelling Salesman Problem

b) A dispatcher presently has six taxicabs at different locations and five customers who have call for service. The mileage from each taxi’s present location to each curstomer is

Customer 1 2 3 4 5
Cab
A 7 2 4 10 7
B 5 1 5 6 6
C 8 7 6 5 5
D 2 5 2 4 5
E 3 3 5 8 4
F 6 2 4 3 4

Determine the optional assignment that will minimize the total mileage.

6. a) Explain the Critical Path method.
b) A project being planned involved the following activities:

Activity Predecessor Duration
A - 14
B A 21
C A 50
D B 14
E C,D 30
F E 10

Construct the network.
Determine expected project completion time.
Determine free slack and total slack.

7. a) Explain the Graphical Method for solving a Game.

b) Find the Optimal solution for the following game using Graphical method:

Player B
1 2 3 4 5

Player A 4 2 5 -6 6
7 -9 7 4 8
8. a) Explain the Integer Programming problem.

b) Explain the Branch and Bound Technique for solving an Integer Programming Problem





About us | SiteMap | Terms of use | Privacy Policy | Disclaimer | Contact us | ©2010 K2Questions.com